Reports
Every screened site report, its findings, and the decision taken
corpus
7 documents
searchable
73 chunks
Every screened site report, its findings, and the decision taken
| issue | severity | governing rule | recommended action |
|---|---|---|---|
| Guardrail on the east run of the level-4 platform was removed and not reinstalled, exposing a 12m open edge. | high | [OSHA 3150 Scaffold Guide, Sec 1926.451(g)(4), p.42] | Reinstall the guardrail along the open edge of the level-4 platform immediately. |
| Two labourers were observed on the scaffold without hard hats during the afternoon pour. | medium | [OSHA 3150 Scaffold Guide, Sec 1926.451(h)(1), p.9] | Ensure all workers on the scaffold wear hard hats at all times. |
Daily Site Report - Tower B, 14 Mar. Crew of 9 on levels 3-5. Formwork stripped on level 4. Scaffold erected on the north face to 8m. The guardrail on the east run of the level-4 platform was removed yesterday to move materials and has not been reinstalled; the open edge is roughly 12m long. Crew continued working from that platform all shift. Two labourers were observed on the scaffold without hard hats during the afternoon pour. Concrete pour on level 3 completed at 15:40. Weather dry. Delivery of rebar arrived 11:00, offloaded by crane without incident.
this decision predates the identity layer — status was recorded, the person and the moment were not